Projects

Projects

  • Successfully Commissioned 3x6000kva, 11kv Hydel Gensets at M/S. International Power Corporation Limited. (Year 1998 – 1999).
  • Successfully Commissioned 3x6000kva, 11kv Hydel Gensets at M/S. Atria Power Corporation Limited. (Year 1999 – 2000).
  • Successfully Commissioned 1x40000kva, 11kv Thermal Gensets at M/S Shriram Fertilizers Limited. (Year 2000 – 2001).
  • Successfully Commissioned 2x50000kva, 11kv Thermal Gensets at M/S Jindal Vijay Nagar Steels Limited. (Year 2001 – 2002).
  • Successfully Commissioned 8x20500kva, 11kv Thermal Gensets at M/S Jindal Steels & Power Limited. (Year 2002 – 2003).
  • Successfully Commissioned 150x600kw, 690volts Wind Farm Gensets at M/S Vestas India Limited. (Year 2004 – 2005) No. 2 1st Cross MEI Layout beside BBMP Office Hesaraghatta main road Nagasandra Post Bagalagunte Bangalore-560073 Rathasya Power Consultants
  • Successfully Commissioned 4x1000kva, 11kv Dg Sets At M/S Dewa, (Dubai Electricity And Water Authority) Dubai. (Year 2006 – 2007)
  • Successfully commissioned 220/110KV Substation At vajmangala Mysore.
  • Testing Of All Panels At Factory For Functional And Operational Tests.
  • Successfully Completed Rla Studies Of Various Thermal Power Plants Through Central Power Research Institute (Ministry Of Power) At 4x100Mw Bhathginda Thermal Power Plant, 8*100Mw Thau Devilal Thermal Powerplant,8x50Mw hrdagang Thermal Power Plant,4x50Mw Bhusawal Thermal Power Plant.( Year 2006 – 2007)
  • Successfully Commissioned 2x500Mva 400/220kv Station At Hoody, Nelamangla & Hirrur In Karnataka, 2x100Mva 220/110 Kv Substations At Gulbarga, Ranebennur, Gadag & Honnali, 110 /33/11 Kv Substation At Gajendragada, Lakshmeshwar, Ron, Naragal, Gadag, Rathihalli, Hirekerur, 40Mva 66/33kv Pooling Substations At Chitradurga, Baswapatna, Gajendragada, Bettadnagenhalli, Hatti Gold Mines Chitradurga, Iemangala & Pandrahalli. (Year 2006 – 2007).
  • Successfully Commissioned 4 X 3.75 Mw 6.3kv At Saui – Sap River (Vietnam Through Tata International Limited). No. 2 1st Cross MEI Layout beside BBMP Office Hesaraghatta main road Nagasandra Post Bagalagunte Bangalore-560073 Rathasya Power Consultants
  • Successfully Completed Harmonic Measurement For A Steel Plant (Aden Steels) Republic Of Yemen
  • Successfully Commissioned 35Mw Combined Cycle Gas Turbine At Kotakinabalu, Malaysia
  • Successfully commissioned M/s. Thendaho sugar Factory 26000 TCD ,150 TPH of 2 Boilers(Phase 1) at Ethiopia.(Year of 2013-2014)
  • Doing R&M Work at somanahalli PGCL 400/220 KV Substation M/s. KGN Electricals Thumkur.
  • Successfully Commissioned 2x10MvA 66/11KV At Kolar road Narsapura M/s. Standard Transformers (year of 2014)
  • Successfully Completed Room Acoustic treatment @ Prestige tech park Marthalli. M/s. Eurotech pvt ltd. (Year of 2013)
  • Successfully commissioned Byrkoor 66/11KV Sub Station for M/s. KPTCL Kolar.(Year of 2013)
  • Successfully commissioned 16/25MVA transformer @ Thandga110/11KV Sub Station for M/s. KPTCL Thumkur. (Year of 2013)
  • Successfully commissioned 2x6.8MW Pathri Hydro power project @ Utharakhand. M/s. Andritz Hydro power pvt ltd.(Year of 2013) No. 2 1st Cross MEI Layout beside BBMP Office Hesaraghatta main road Nagasandra Post Bagalagunte Bangalore-560073 Rathasya Power Consultants
  • Successfully commissioned 2x4MW HPP Hydro project @ Jharkhand. M/s. HPP
  • Successfully commissioned 4x42MW Periyar power house @ Kumili. M/s. Andritz hydro.(Year of 2013)
  • Successfully commissioned Kora 66/11KV Sub Station Wiring and Testing & Commissioning. M/s. KGN Electrical Thumkur.(Year of 2014).
  • Successfully commissioned 66/11KV Sub Station @ Kamasamudra.(Year of 2014)
  • Successfully commissioned 11KV Switch Yard Errection and testing and commissioning. M/s. Axis Bank business data continuity center.(Year of 2014)
  • Successfully commissioned 66/11KV Sub Station for M/s.KPTCL @ N.G Hulkur Kolar (Year of 2014)
  • Successfully commissioned M/s. Barooka 9X2.5 MW wind power plant complete testing & Commissioning. @ Belagavi.
  • Successfully commissioned 2X2.5MW Hydro power plant @ Harohalli M/s. Raising sun hydro.
  • Successfully commissioned M/s. Bosch Manufacturing ltd. 66/11KV Substation at Bidadi Ramanagara
  • Installation and Commissioning Of Centrifugal Air Compressors at IOCL, HPCL, BPCL, Foxconn, Moser Baer, Hona Seil Cars India Limited and Reliance.
  • Complete solution for Erection and Installation, Testing and Commissioning in power sector.
  • In view of maintaining customer satisfaction reviewing repeat orders from our entire major consultants.
  • Executed projects for applications such as Steel industries, Cement, Sugar plants, power plants such as Hydro, Wind, Thermal and Solar power plants.
  • Successfully commissioned M/s. Belectric Photovoltaic India Pvt Ltd., 2X50MW Solar PV Power Plant Project at Pavagada Solar Park, Karnataka.
  • Successfully commissioned M/s. TATA Power Solar Systems., 150 MW Vijayapuri.
  • Successfully commissioned M/s. Aditya Birla Renewables Ltd., 28 MW Solar Power Plant at Bijapura.
  • Successfully commissioned M/s. Maruthi Power Gen Pvt Limited, 3 x 8MW power project, Hongadahalla.
  • Successfully commissioned M/s. SLV Power Pvt Ltd, 3 x 8MW ANIYUR MHS, Mangalore.
  • Successfully commissioned M/s. Four EF Constructions Pvt Ltd, 38 MW Wind Power Project, Balenahalli Village, Chitradurga.

Laisioning work carried out for following customers

  • M/s. Fortum Finnsurya Energy Pvt Ltd. 100MW.
  • M/s. TATA Power Ltd, 150MW.
  • M/s. ABReL. 28MW.
  • M/s. Maruthi Power Gen- 24MW.
  • M/s. SLV Power Pvt Ltd. 24MW.
  • M/s. Clean Max Solar. 48MW.
  • M/s. Sitac Management & Development Private Limited. 300MW

Survey work carried out for following customers:

  • Pawagada 450Acres Solar Park. Scope of works: Trenches, Transmission Lines, Solar Panel Pointing.
  • M/s. ABRel
  • M/s. Fiza Developers., Balenahalli.
  • M/s. Ampyrenergy., Hiriyur.

Present running project:

  • Hiriyur 100MW solar land acquisition and total ETC
Top